Ongoing General Updated 6 days, 4 hours ago

Hydropower Project Extensions

Nepal extends deadlines for 27 hydropower projects

What happened

Nepal’s power authorities have extended timelines for dozens of delayed hydropower projects while weighing flood damage, financing constraints and transmission bottlenecks.

Timeline

Flood Damage Cited
Oct 07, 00:33

The Nepal Electricity Authority said flood damage, financing problems, and unfinished transmission infrastructure justified the deadline extensions for the 27 projects. The move is meant to protect viable projects while holding back developers with little real progress.

Deadline Extensions Approved
Oct 05, 14:46

The Nepal Electricity Authority extended the Required Commercial Operation Date for 27 hydropower projects totaling 540.47 MW. The new process groups projects by physical progress and compliance to make extensions more transparent and accountable.