Hydropower Project Extensions
Nepal extends deadlines for 27 hydropower projects
What happened
Nepal’s power authorities have extended timelines for dozens of delayed hydropower projects while weighing flood damage, financing constraints and transmission bottlenecks.
Timeline
Upper Karnali Advance Ordered
Oct 09, 17:09The Investment Board said Upper Karnali construction will move ahead immediately as part of a broader push to accelerate delayed hydropower projects. The project has faced years of funding delays and legal disputes over financial closure and shareholding changes.
Flood Damage Cited
Oct 07, 00:33The Nepal Electricity Authority said flood damage, financing problems, and unfinished transmission infrastructure justified the deadline extensions for the 27 projects. The move is meant to protect viable projects while holding back developers with little real progress.
Deadline Extensions Approved
Oct 05, 14:46The Nepal Electricity Authority extended the Required Commercial Operation Date for 27 hydropower projects totaling 540.47 MW. The new process groups projects by physical progress and compliance to make extensions more transparent and accountable.
Latest Coverage
Upper Karnali project set to advance after years of funding delays
Oct 19The long-delayed 900-megawatt Upper Karnali Hydropower Project is set to move toward construction after the Investment Board decided to facilitate the immediate start of …
kathmandupost.com BusinessIBN clears Rs 21.17 billion for two hydropower projects
Oct 11Investment Board Nepal has approved Rs 21.17 billion for two semi-reservoir hydropower projects in Kathmandu. The board also moved to accelerate the Arun-3 and …
myrepublica.nagariknetwork.com BusinessDecision to approve investment in two semi-reservoir hydropower projects
Oct 09The Investment Board has approved investment in two semi-reservoir hydropower projects in Nepal, including the Narkhola and Sani Bheri-3 projects. The board also said …
risingnepaldaily.com BusinessSaving Hydro, Not Delays
Oct 07The Nepal Electricity Authority has extended construction deadlines for 27 hydropower projects, citing flood damage, financing issues, and unfinished transmission infrastructure. The move aims …
myrepublica.nagariknetwork.com BusinessNEA extends deadlines for 27 hydropower projects totaling 540 MW
Oct 05The Nepal Electricity Authority has extended deadlines for 27 hydropower projects totaling 540.47 MW, offering relief to developers with genuine construction progress. The new …
myrepublica.nagariknetwork.com BusinessHeavy rain forecast puts hydropower projects in Gandaki on high alert
Sep 25Hydropower projects across the Gandaki basin have been placed on high alert as Nepal prepares for heavy rainfall from September 25 to 27. The …
myrepublica.nagariknetwork.com Environment