Decision to approve investment in two semi-reservoir hydropower projects

Summary

The Investment Board has approved investment in two semi-reservoir hydropower projects in Nepal, including the Narkhola and Sani Bheri-3 projects. The board also said commercial power production from Arun-3 will be ensured by February 2028 and that Upper Karnali construction will move ahead immediately.

Key Points
  • The Investment Board approved investment in the Narkhola Semi-Reservoir Hydropower Project and the Sani Bheri-3 Semi-Reservoir Hydropower Project.
  • The 68th meeting was chaired by Prime Minister Balendra Shah and endorsed the two projects worth over Rs 21 billion combined.
  • Commercial power production from the Arun-3 Hydropower Project is expected by February 2028, and Upper Karnali construction will be forwarded immediately.
  • The Board said it would use the Swiss Challenge method when needed to prioritize renewable energy projects.