Railway Construction

Summary

Nepal’s East-West Electric Railway project has made only 3.58 percent progress by mid-July 2025, while its estimated cost has climbed to Rs. 1017 billion. Delays in land acquisition, financing, staffing and environmental clearance have slowed work on the national pride project, with no budget earmarked this fiscal year.

Key Points
  • Nepal’s limited railway network currently includes the Janakpur-Jayanagar passenger line and freight links at Sirsiya-Birgunj and Biratnagar.
  • The East-West Electric Railway project, launched in 2008, has faced persistent delays because of unclear investment modality, land acquisition problems and institutional confusion.
  • An Office of the Auditor General report says the project had achieved only 3.58 percent progress by mid-July 2025, while its cost estimate rose to Rs. 1017 billion.
  • The government has not allocated a budget for the project this fiscal year, even as it plans to extend the line toward Ratanpur and connect it to the Kathmandu-Tarai/Madhes Fast Track.