Absence of funds, institution leaves East-West Railway stuck
Summary
The East-West Electric Railway project remains stalled amid no budget allocation, an unresolved investment model and land acquisition challenges. Costs have risen to Rs. 1,017 billion while physical progress has reached only 3.58 per cent, with completion now projected around mid-July 2030.
Key Points
- The East-West Electric Railway has made only 3.58 per cent progress since 2009/10, while its estimated cost has climbed to Rs. 1,017 billion.
- The Office of the Auditor General says the project faces delays because of an unclear investment model, land acquisition hurdles and shortages of railway human resources.
- The government has scrapped the Department of Railway and is transferring authority to the Railway Board, but no budget has been allocated for the project.
- Land acquisition and local disputes continue to slow work on key sections, including Bardibas–Inaruwa and the planned extension toward Ratanpur.