Four-lane bridge construction in Damuali reaches 84% physical progress

Summary

Physical progress of the four-lane bridge in Damuali over the Madi River has reached 84%, with economic progress at 81.2%. The project aims to complete within the extended deadline.

Key Points
  • The four-lane bridge construction in Damuali has reached 84% physical progress.
  • Economic progress of the project stands at 81.2%.
  • The bridge is 315 meters long with six spans and features the country's first single monolithic structure of 23 meters width.
  • The construction is being carried out by Annak ZDJC JV and aims to finish within the extended deadline.