Tanahu Hydropower Project Reaches 75% Completion
Summary
The Tanahu Hydropower Project in Rishing Rural Municipality has reached 75% completion, progressing across dam construction, main tunnel, powerhouse, and transmission line work.
Key Points
- Tanahu Hydropower Project with 140 MW capacity has achieved 75% overall progress.
- Work on three packages: dam and related structures, main tunnel and powerhouse, and transmission line are ongoing.
- Package 1, covering dam and related structures by Songda Kalika JV, has reached 57% progress.
- Seti River diversion completed in November 2023, enabling further construction phases.