One-way concreting completed on the eastern Daunne section of Mahendra Highway
Summary
One-way concreting on the eastern Daunne section of Mahendra Highway between Dumkibas and Bardaghat has been completed, with traffic expected to resume within two weeks. The highway expansion project overseen by China State Construction Engineering Corporation is about 85% complete.
Key Points
- One-way concreting completed on the eastern Daunne section of Mahendra Highway between Dumkibas and Bardaghat.
- The highway expansion project is divided into eastern and western sections managed by China State Construction Engineering Corporation.
- About 85% of the overall Mahendra Highway construction work has been finished.
- Traffic along the Daunne stretch is expected to fully resume before mid-July, with project completion targeted for the third week of July.