Tamakoshi V hydropower project reaches 30 percent completion

Summary

The 99.8-megawatt Tamakoshi V Hydropower Project in Dolakha has reached 30 percent completion after a 10-month halt over forest land-use permissions. Construction has resumed across multiple sites, with the project now aiming to finish within 15 to 18 months.

Key Points
  • The Tamakoshi V Hydropower Project in Dolakha has reached 30 percent completion after construction resumed following a 10-month delay.
  • Chinese contractor Sinohydro is carrying out the civil works, while another Chinese firm, Hangzhou Jianghe Hydroelectric Science and Technology, has been awarded the electromechanical package.
  • The project’s schedule was pushed back because of delays in getting permission to use government forest land, and the company is negotiating contract changes over tunnel lining costs.
  • If the tunnel must be lined with concrete, the project may not start generating electricity until April 2030.