128MW Tamor Mewa Hydropower Project in Taplejung Achieves 35% Physical Progress

Summary

The 128 MW Tamor Mewa Hydropower Project in Taplejung has reached 35% physical progress, with work underway at the headworks, settling basin, tunnel and powerhouse. The project says land acquisition has been completed and construction is advancing with financing arranged through a consortium led by Siddhartha Bank and supported by the Asian Development Bank.

Key Points
  • The 128 MW Tamor Mewa Hydropower Project in Taplejung has achieved 35 percent physical progress.
  • Construction is ongoing at the headworks, settling basin, headrace tunnel and powerhouse site.
  • The project’s financial management has been completed in collaboration with the Asian Development Bank, led by Siddhartha Bank Limited, with Machhapuchchhre Bank Limited as co-leading bank.
  • Company chairman and managing director Sudeep Kumar Chaudhary visited the site and said the project is expected to be completed on time.
Article image