Lower Arun project targets power generation from December 4, 2030; contract tender issued
Summary
The 669 MW Lower Arun Hydropower Project is targeting electricity generation from December 4, 2030, after entering the implementation phase and inviting a contract worth about INR 11.4921 billion. The government also blacklisted 20 firms and companies and reported progress on complaints received through Hello Sarkar.
Key Points
- The 669 MW Lower Arun Hydropower Project aims to begin electricity generation on December 4, 2030.
- The Office of the Prime Minister and Council of Ministers said the project has entered the implementation phase.
- A contract worth about INR 11.4921 billion has been invited for the project.
- The Public Procurement Monitoring Office blacklisted 20 firms and companies and reported progress on grievance complaints through Hello Sarkar.