Construction of Tulsipur-Ghorahi road resumes after seven-year delay
Summary
Construction of the 21.58-kilometre Ghorahi-Tulsipur four-lane road has resumed after years of delay, but only 17 percent of the work has been completed in the past 15 months. The project, financed by India’s Export-Import Bank, is now expected to be completed by July 8, 2028.
Key Points
- Construction on the Ghorahi-Tulsipur road has resumed after a seven-year delay, but progress remains slow.
- Only 17 percent of the work has been completed in the last 15 months, with about Rs 379.5 million spent so far.
- The project was first awarded to Tathya Engineering and Infra Project, but the contract was terminated in 2023 after the company failed to finish the work.
- A new contractor, Diwa/Bandan Bhagwati JV, resumed work in November 2025 and is targeting completion by July 8, 2028.