Karnali Province Ministry Struggles with Project Implementation Amidst E-Bidding System Delays

Summary

Karnali Province’s Ministry of Physical Infrastructure and Urban Development has only moved about 3 percent of this fiscal year’s projects into implementation, with e-bidding delays blamed for the slowdown. The ministry says contracts should start opening quickly now that the system is operational, but development spending remains far below target.

Key Points
  • The ministry has 528 projects this year, but only 12 have entered the contracting process so far.
  • Officials blame delays in the new e-bidding system for slowing project implementation across districts.
  • Only 6.44 percent of the ministry’s development budget has been spent by the end of Kartik.
  • Last year, contracts for 245 of 512 new projects had already been awarded by this time, showing a much faster pace.
Article image