Electricity restored in Battar, Trishuli Bazar areas after Bhote Koshi flood

Summary

Electricity has been restored in Battar, Trishuli Bazar and surrounding areas of Nuwakot after flood damage in the Bhote Koshi River disrupted the regular supply system. The Nepal Electricity Authority is repairing damaged infrastructure while using an alternative transmission arrangement to keep services running.

Key Points
  • Electricity service has resumed in Battar and Trishuli Bazar after flood damage in the Bhote Koshi River affected the regular supply system.
  • The Nepal Electricity Authority restored power by charging the Balaju-Trishuli and Chapali-Devighat 66 kV transmission lines at 11 kV through an alternative arrangement.
  • The NEA is continuing repair and rehabilitation work to restore electricity in all affected areas.
  • The affected areas include Battar, Trishuli Bazar and surrounding parts of Nuwakot.