400kV Transmission Line Construction Resumes After Local Dispute Resolution

Summary

Construction of the Hetauda-Dhalkebar-Duhabi 400kV transmission line has resumed after resolving local compensation disputes, aiming to strengthen Nepal's electricity supply and grid reliability.

Key Points
  • Construction of the Hetauda-Dhalkebar-Duhabi 400kV Transmission Line has resumed after resolving local disputes.
  • Landowners accepted compensation following discussions led by Energy Minister Biraj Bhakta Shrestha.
  • Three towers have been constructed in Hetauda, with two more under erection; foundation work for all towers is complete.
  • Delays risk wasting 800 megawatts of electricity during the rainy season if the line is not operational this financial year.