Work resumes on Hetauda-Dhalkebar transmission line after a long-standing dispute

Summary

Construction has resumed on the Hetauda-Dhalkebar-Inaruwa 400 kV transmission line after local disputes caused delays. Compensation and security measures are central to resolving the conflict.

Key Points
  • Construction work on the Hetauda-Dhalkebar transmission line has resumed after months of local disputes.
  • Work was stalled mainly in wards 15, 16, and 17 of Hetauda Sub-metropolitan City due to resident objections.
  • Police have been deployed to maintain security at construction and wire stringing sites.
  • A compensation evaluation committee has been formed to address disputed land compensation issues.