Narayangadh-Butwal Road Expansion Project Enhances Safety on Completed Sections

Summary

Road safety improvements such as lane painting, barriers, and signage are underway on completed sections of the Narayangadh-Butwal Road Expansion Project, which is nearing completion in Nawalpurasi.

Key Points
  • Road safety work has begun on completed sections of the Narayangadh-Butwal Road Expansion Project's eastern section.
  • Most road construction in the 65 km eastern section is 81 percent complete with about 7 km still unpaved.
  • The project is divided into two sections totaling 113 kilometers, funded by an Asian Development Bank loan totaling Rs 16.99 billion.
  • The deadline for the project completion has been extended for the fourth time, now set for next Saun.