Nagdhunga–Muglin road widening delayed as utility poles hold up work

Summary

The Nagdhunga–Muglin road widening project is delayed primarily due to electricity pole removal issues, which have held up construction and paving work along several sections of the road.

Key Points
  • Three years into the Nagdhunga–Muglin road widening project, utility pole removal delays have slowed construction.
  • Contracts were awarded before completing preparatory work, causing unresolved pole relocation and compensation issues.
  • The Nepal Electricity Authority and government agencies blame each other for pole relocation delays.
  • Work progress varies across sections; the project is currently 49 percent complete overall, with some stretches facing material shortages and local opposition.