Sanima Middle Tamor Hydel Project resumes power operation

Summary

The Sanima Middle Tamor Hydropower Project in Taplejung has resumed power generation after being shut for nearly a month due to technical issues, following maintenance and repairs.

Key Points
  • The Sanima Middle Tamor Hydropower Project, generating 73 MW, has resumed operations after nearly a month of shutdown.
  • Technical glitches in the powerhouse and other facilities caused the halt in power generation.
  • The shutdown period was utilized to fix technical issues and carry out regular maintenance.
  • The project is the largest hydropower project in Taplejung district and is connected to the central grid via Basantapur Sub-Station.
Article image