Araniko Highway: Sanga-Dhulikhel road expansion drive expedited
Summary
The expansion drive on the Sanga-Dhulikhel road section of the Araniko Highway is progressing with an extended deadline to December 2025 and focused blacktop work in several areas.
Key Points
- Activities for the road expansion on Sanga-Dhulikhel section of the Araniko Highway have been expedited.
- Lama Construction Pvt Ltd holds the Rs 4.5 billion contract to build eight kilometres of road.
- Only 60 percent of the construction was completed by the original deadline.
- Current focus is on blacktopping roads around Dhulikhel and Pulbazaar-Janagal areas, with culvert installation planned at Banepa.