Minister Ghising wants Muglin-Pokhara road completed promptly
Summary
Minister Kulman Ghising has urged the contractor to promptly complete the Muglin-Pokhara road, with current progress at nearly 60% physical completion and multiple bridges constructed along the route.
Key Points
- Minister Kulman Ghising directed the contractor to expedite the completion of the Muglin-Pokhara road.
- Physical progress of the road expansion has reached 59.76 percent and financial progress 47.80 percent.
- A four-lane asphalt road has been completed on 29.61 km and two-lane on 7.79 km of the road stretch.
- Out of 12 bridges planned, 11 have been constructed with one bridge over the Seti River still under construction.