Minister Ghising directs fast-track completion of Muglin–Pokhara road
Summary
Minister Kulman Ghising has directed fast-track completion of the Muglin–Pokhara road, with project progress at nearly 60 percent and a targeted deadline of December 31.
Key Points
- Minister for Physical Infrastructure and Transport Kulman Ghising has instructed contractors to expedite the Muglin–Pokhara road construction.
- The project has reached 59.76% physical progress and 47.80% financial progress.
- A four-lane asphalt road has been completed on 29.61 km, and two-lane asphalt on 7.79 km of the stretch.
- Eleven out of twelve planned bridges have been completed, with one still under construction over the Seti River.