Minister Ghising wants Muglin-Pokhara road completed promptly
Summary
Minister Kulman Ghising inspects progress of Muglin-Pokhara road project, urging timely completion to facilitate smooth traffic.
Key Points
- Minister Kulman Ghising directed the contractor to expedite completion of the Muglin-Pokhara road.
- The project has achieved 59.76% physical progress and 47.80% financial progress so far.
- Out of 48.88 km, 37.4 km has the first asphalt layer laid; 29.61 km is four-lane asphalt road.
- Eleven out of 12 bridges are constructed, with one bridge over Seti River still under construction.