Narayanghat-Butwal road section achieves 76% physical progress
Summary
The Narayanghat-Butwal four-lane road project has achieved 76% physical progress along its 65-kilometre stretch, with efforts continuing to complete remaining bridge blacktopping and culvert construction by the fiscal year's end.
Key Points
- The Narayanghat-Butwal four-lane road has reached 76 percent physical progress.
- The project has received a fourth deadline extension, targeting completion by the end of this fiscal year.
- Blacktopping of several bridges including Jayashree, Arunkhola, Dumkibas, and Chormara remains incomplete.
- Culvert construction in the Daunne area is in its final phase and expected to complete within four and a half months.
Other Coverage of This Story
Narayanghat–Butwal four-lane project reaches 76% physical progress
thehimalayantimes.comThe Narayanghat–Butwal four-lane road project has reached 76% physical progress, with bridge and blacktopping works ongoing and a completion target …
Dec 04, 2025 15:41Narayanghat-Butwal road section achieves 76% physical progress
ratopati.comThe Narayanghat-Butwal four-lane road project has achieved 76% physical progress with work ongoing to complete remaining blacktopping and bridge construction …
Dec 04, 2025 14:26