Construction of Doda River Bridge reaches 90pc completion

Summary

The construction of the Doda River Bridge in Mahendranagar has reached 90% completion, with expected completion by January. The bridge will improve travel for residents of Lajhadi, Shuklaphanta, and Krishnapur.

Key Points
  • Construction of the Doda River Bridge has reached 90 percent completion.
  • The bridge's superstructure is finished; work is ongoing on wall construction and soil filling.
  • The project began in 2016 with a three-year timeline but has faced repeated delays.
  • Completion is expected by the end of Poush (January), requiring additional funds of Rs 40 million.