Five years on, Dharan bridge still incomplete

Summary

The Leduwa stream bridge in Dharan remains only 64% complete after five years, exposing locals to danger during monsoon. Repeated delays, disputes, and court interventions have stalled the project, impacting education, healthcare, and local trade.

Key Points
  • The Leduwa stream bridge in Dharan has only reached 64% completion after five years since July 2020.
  • The bridge was originally contracted for completion by July 2021 with a budget of Rs12.1 million under World Trade Construction Company.
  • Repeated delays and disputes have stalled the project, causing locals to risk unsafe crossings during monsoon to access essential services.
  • The construction contract is being terminated by the government, but a court stay order obtained by the company has stalled this action.