Koteshwor Underpass to Be Completed by 2090 BS, Here's What the New Structure Will Look Like
Summary
The Koteshwor Underpass project, funded by a Japanese loan, is planned for completion by 2090 BS with key structures including flyovers and a tunnel near Tribhuvan International Airport.
Key Points
- The Koteshwor Underpass is scheduled to be completed by 15th Bhadau 2090 BS (August 2023 CE).
- A Japanese loan of approximately 30 billion Nepalese rupees finances the project.
- Key structures include a 664-meter flyover from Tinkune to Tribhuvan International Airport, a 700-meter tunnel at the airport, and a 238-meter flyover linking the airport to Manohara via Jadibuti.
- The consulting company for DPR and EIA will be selected by March 2024, with construction targeted to finish within 52 months after contract signing in April 2028.