Bheri Babai Diversion Project stumbles despite early tunnel success

Summary

The Bheri Babai Diversion Project in western Nepal completed its tunnel phase early but has faced significant delays and challenges, with only 69% progress after over a decade and completion pushed to 2027-28.

Key Points
  • The Bheri Babai Diversion Project completed a 12-km tunnel ahead of schedule in April 2019, a first in Nepal.
  • Overall project progress stands at 69%, with delays pushing the completion deadline to fiscal year 2027-28.
  • Challenges include slow budget approvals, import delays, local resistance, compensation disputes, and procedural hurdles.
  • The project aims to irrigate 51,000 hectares and generate 46 MW of electricity, impacting agriculture and energy in Banke and Bardiya districts.