Court case threatens to delay Ilam fast-track, residents demand fresh contract

Summary

Residents of Ilam are pressing the government to begin a fresh contract for the Belase–Golakharka section of the Mechi Corridor after the former contractor challenged the termination in court. The delay has raised fears of another monsoon-related transport crisis for Ilam, Panchthar and Taplejung.

Key Points
  • Residents fear the court challenge will further delay the Belase–Golakharka section of the Mechi Corridor, also known as the Ilam–Jhapa Fast Track.
  • The former contractor failed to complete even half of the 9.5-kilometre road section despite multiple extensions, prompting the Road Division Office to terminate the contract.
  • Local leaders say the unfinished road is crucial as an alternative route when landslides block the Mechi Highway's Rajduwali section during the monsoon.
  • Minister Sunil Lamsal says the government will arrange funding and approvals for a fresh procurement process, but no new tender has started yet.