Mountains to become visible again as power cables go underground
Summary
Pokhara’s Lakeside is set to regain its mountain views as electricity cables are moved underground under a major infrastructure project. The work, funded by the Asian Development Bank and implemented by the Nepal Electricity Authority, will remove thousands of overhead poles across Pokhara and Bharatpur.
Key Points
- Electricity cables are being shifted underground in Pokhara’s Lakeside area to restore mountain views and improve the surroundings.
- The Pokhara-Bharatpur Distribution System Strengthening Project is expected to remove around 6,000 electricity poles in Pokhara.
- The project is 82% complete in Pokhara and 95% complete in Bharatpur, with underground supply expected to start by the end of Chaitra in Pokhara.
- The project is being funded by a concessional loan of around Rs. 3 billion from the Asian Development Bank, and Tata Projects won the contract in 2022.