Second Mahadevtar tunnel bore breaks through Kathmandu-Tarai Expressway
Summary
The second bore of the Mahadevtar tunnel on the Kathmandu-Tarai Expressway has broken through, with President Ramchandra Paudel attending the ceremony. The 70.977-kilometre expressway remains about 50 percent complete as land disputes, tree clearance delays and other setbacks continue to push back the deadline.
Key Points
- The 3.445-kilometre Mahadevtar tunnel on the Kathmandu-Tarai Expressway has achieved a breakthrough on the bore carrying traffic from Nijgadh toward Kathmandu.
- President Ramchandra Paudel attended the ceremony, along with Infrastructure Minister Sunil Lamsal and Chief of Army Staff Ashok Raj Sigdel.
- The 70.977-kilometre expressway from Khokana in Lalitpur to Nijgadh in Bara is only about 50 percent complete after nine years under the Nepali Army.
- Land acquisition, tree clearance delays and unresolved decisions in the Khokana-Dukuchhap section continue to delay the project, whose estimated cost is Rs211.93 billion.