Nepal gets India’s approval to import 350MW and export 56MW

Summary

Nepal has received India’s approval to import up to 350MW of electricity this winter and to export 56MW from three hydropower projects through the Indian Energy Exchange. The Nepal Electricity Authority expects domestic generation to fall short for four months during the dry season after flood damage to hydropower projects and transmission lines.

Key Points
  • Nepal can import up to 350MW of electricity from India during the dry season to cover a projected shortfall in domestic generation.
  • The Central Electricity Authority has also approved export of 56MW from three hydropower projects through the Indian Energy Exchange.
  • Imports will be allowed from November 17 to July 31, 2027, but not during the morning and evening peak hours.
  • The NEA says flood damage in the Bhotekoshi river area and seasonal low output could force higher imports through mid-April 2027.