Construction of Matatirtha–Chobhar 132 kV transmission line completed

Summary

Construction of the Matatirtha–Chobhar section of the 132 kV transmission line has been completed, improving electricity supply in Kathmandu Valley. The line is scheduled to be charged on Friday, while work continues on the underground Chobhar–Patan line and related substation upgrades.

Key Points
  • The Matatirtha–Chobhar section of the Thankot–Chapagaun–Bhaktapur 132 kV Transmission Line Project has been completed and will be charged on Friday.
  • NEA says the line will help balance electricity demand and supply in Kathmandu Valley and surrounding areas, especially during the winter season.
  • The Chobhar Substation has been built as an alternative after local obstruction delayed work in Khokana, Bungamati, Harisiddhi and Lamatar.
  • Further work is underway on a 4.5-kilometre underground 132 kV line from Chobhar to Patan and on upgrading the Patan Substation.