Flood Damage Halts 6 MW Relekhola Hydropower Project in Myagdi

Summary

Floodwaters have damaged the dam and transmission infrastructure of the 6 MW Relekhola Hydropower Project in Myagdi, forcing it to halt electricity generation. Landslides and blocked access roads are slowing repair and restoration work.

Key Points
  • The 6 MW Relekhola Hydropower Project in Annapurna Rural Municipality-4, Narchyang, Myagdi has fully stopped power generation after floodwaters entered its dam.
  • Project Chief Darshan Kafle said heavy rainfall and flooding between September 24 and 27 caused significant damage.
  • Landslides have blocked access roads, making it difficult for personnel to reach the site and carry out repairs.
  • Several transmission line towers and wires connected to the national grid through the 220 kV Dana Substation have also been damaged.