Abunwa-Pauwatar road project makes 30% progress in four years

Summary

The Abunwa-Birdi-Sera-Pauwatar road blacktopping project in Gorkha has reached only 30% progress in four years, with officials blaming the contractor for repeated delays. Local residents and municipal leaders are calling for action as the poor road condition continues to affect travel, health, education and the local economy.

Key Points
  • The Abunwa-Birdi-Sera-Pauwatar road blacktopping project has achieved only 30% physical progress despite four years of work.
  • Officials say contractor Amar VBIEPL JV has failed to mobilize enough manpower and equipment, slowing construction of the sub-base, drainage and road bends.
  • Palungtar Municipality leaders and residents say the delay has badly affected travel, patients, students, farmers and the local economy.
  • The municipality has urged authorities to consider canceling the contract and finding an alternative process after legal procedures.