Krishna Bhir Road Section to Reopen in Three Days

Summary

The Krishna Bhir road section is set to reopen within three days after a landslide triggered by flooding in the Trishuli River blocked traffic. Road officials say a new track has been completed from the mountainside and work is now underway to prepare the subgrade and lay gravel.

Key Points
  • The Krishna Bhir road section was blocked by a landslide caused by flooding in the Trishuli River.
  • Officials say a new mountainside track has already been completed and subgrade preparation is in progress.
  • Two bulldozers and two excavators are currently being used to improve the grade.
  • Traffic on the road is expected to resume within two to three days after gravel is laid.
Article image