Devighat bridge ready in five days, opens today
Summary
The Nepal Army installed an Acrow bridge at Devighat in Nuwakot within five days, restoring transport links after a flood swept away a permanent bridge in Rasuwa. Pedestrians can use the bridge from today, with vehicles allowed from tomorrow.
Key Points
- The Nepal Army completed installation of an Acrow bridge at Devighat in Nuwakot on Wednesday night after five days of work.
- The bridge restores transport access after a permanent bridge was swept away by the Bhote Koshi flood in Rasuwa.
- The bridge opens to pedestrians from today and to vehicles from tomorrow.
- Home Minister Sudhan Gurung announced the completion on social media.