Prime Minister Balen Shah Informs Parliament About Delayed Rescue Efforts in BhoteKoshi-Trishuli Corridor

Summary

Prime Minister Balen Shah told Parliament that rescue efforts for people trapped in hydropower tunnels in the BhoteKoshi-Trishuli corridor are being delayed by severe flood damage, mud, and difficult terrain. He said eight operational and four under-construction hydropower projects have been hit, disrupting 4,031.1 megawatts of electricity generation.

Key Points
  • Prime Minister Balen Shah said the rescue of people trapped in hydropower tunnels in Rasuwa is being delayed by extreme technical and geographical challenges.
  • He said mud and silt inside the tunnel have blocked access, making it difficult for excavators and helicopters to operate.
  • The government is coordinating with technical expert teams from India, China, and Korea for the rescue operation.
  • Floods damaged eight operating and four under-construction hydropower projects, disrupting 4,031.1 megawatts of electricity generation.