Summary

Heavy flooding from the China side has affected major hydropower projects in Rasuwa and Nuwakot, including several operational plants and projects under construction. The districts together host 9 operational projects generating 359 MW and 5 under-construction projects with a combined capacity of 394 MW.

Key Points
  • Heavy flooding from the China side has impacted key hydroelectric assets in Rasuwa and Nuwakot districts.
  • Rasuwa district has 5 operational hydropower projects with 236 MW and 3 under-construction projects with 342 MW.
  • Nuwakot district has 4 operational projects with 123 MW and 2 under-construction projects with 52.6 MW.
  • The article lists the preliminary status and capacities of major projects such as Upper Trishuli-1, Rasuwagadhi, Sanjen Khola, Trishuli, and Upper Trishuli-3A.