Army's Development Projects Progress Slowly

Summary

The Nepali Army’s major road projects, including the Kathmandu–Terai–Madhesh Expressway, are progressing slowly and facing rising costs due to delays. Several strategic road sections in Karnali and the east have seen incremental work, while the Khandbari–Kimathanka stretch has been handed over after completion.

Key Points
  • The Kathmandu–Terai–Madhesh Expressway has reached only 48.72 percent physical progress after nine years, far behind its original four-year target.
  • Project delays have pushed the expressway’s cost to nearly three times the initial estimate, with Rs 92.68 billion spent so far.
  • The Nepali Army has made progress on other roads, including the Karnali Corridor, Benighat–Arughat–Larkebhanjyang road, and Darcula Tinker section.
  • The 10.51 km Khandbari–Kimathanka section has been completed and handed over to the Department of Roads, improving access toward China.