Jhapa Energy Restores Full 10 MW Power Generation After Inverter Fire

Summary

Jhapa Energy Limited has restored full electricity generation from its 10 MW grid-connected solar project in Shivsatakshi-4, Jhapa after repairing an inverter damaged in a fire. Both 5 MVA inverters are now operational, bringing the plant back to full capacity.

Key Points
  • Jhapa Energy Limited resumed full electricity generation from its 10 MW solar project in Shivsatakshi-4, Jhapa.
  • One of the two 5 MVA inverters caught fire at around 1:42 PM on Jestha 18, 2083, disrupting output from the affected 5 MW unit.
  • The company completed repair and maintenance work on the damaged inverter.
  • Both inverters are now operational, allowing the project to return to full installed capacity.