Road Division Jumla Cancels Contract with M-S BKoi Builders Pvt. Ltd. for Bridge Construction
Summary
Road Division Office Jumla has canceled the contract of M-S BKoi Builders Pvt. Ltd. for failing to begin bridge construction on time in Kalikot district. The company was responsible for bridges over the Tila, Gyaldo and Padimghat rivers under the Surkhet-Mahalekh-Nagma-Gamgadhi road section.
Key Points
- Road Division Office Jumla terminated its contract with M-S BKoi Builders Pvt. Ltd. over delays and non-compliance with the agreement.
- The company was tasked with building bridges over the Tila, Gyaldo and Padimghat rivers in Kalikot district under a Design and Build model.
- Officials said the firm failed to submit the bridge design and environmental study report within the required six months and showed no readiness to start construction.
- The office invoked the Public Procurement Act 2063 and Regulations 2064, and asked the contractor to settle financial matters within 15 days.