Government Terminates Contract with Contech Pvt. Ltd. for Mid-Hilly Highway Project

Summary

The government has terminated Contech Pvt. Ltd.'s contract for incomplete work on the Lamjung section of the Pushpalal (Mid-Hilly) Highway and plans to blacklist the company.

Key Points
  • The government terminated Contech Pvt. Ltd.'s contract for the Pushpalal Highway project due to incomplete work.
  • Contech Pvt. Ltd. failed to comply with instructions and was absent from the site for over 200 days.
  • The project office will proceed with evaluation and financial settlement following the contract termination.
  • Contech Pvt. Ltd. is recommended for blacklisting by the Public Procurement Monitoring Office.