Three years on, Narayani iconic bridge project yet to take shape
Summary
Three years after the contract, the Narayani iconic bridge connecting Narayangarh and Gaindakot has seen minimal progress, with only foundation work underway due to design approval delays.
Key Points
- The Narayani iconic bridge project contract was signed in June 2023 with Tundi Construction.
- Design revisions delayed approval by around 16 months, affecting construction progress.
- Currently, only foundation work and pile testing are underway, with tower construction expected after the monsoon.
- The bridge will cost Rs1.68 billion, span 420 meters, and is intended to ease traffic bottlenecks between Narayangarh and Gaindakot.