Tanahun Hydropower Dam Construction Reaches 50 Percent Completion
Summary
The construction of the main dam under Package-1 of the Tanahun Hydropower Project in Rishing Rural Municipality, Tanahun, has reached 50 percent completion with significant progress in concrete placement and supporting infrastructure.
Key Points
- The main dam of the Tanahun Hydropower Project has reached 50 percent completion.
- A total of 4,24,120 cubic meters of concrete has been placed out of the required 850,000 cubic meters.
- The project began construction on Chaitra 7, 2081 BS.
- Package-1 is being executed by Song Da Kalika Joint Venture and has achieved an overall progress of 59 percent.