Arniko Highway Road Upgrade Faces Delays Due to Material Shortage
Summary
The upgrade and blacktopping of the Dhulikhel-Khawa section of the Arniko Highway is delayed due to a shortage of construction materials, affecting local residents and travelers.
Key Points
- The Dhulikhel-Khawa section of Arniko Highway upgrade has reached its final stage but faces delays due to material shortages.
- 2.5 km of the 4 km road section has been blacktopped, with 1.5 km remaining.
- Contract cancellation and rebidding have occurred due to delays, with a new budget of 42 crore rupees allocated.
- Local residents are disappointed by the slowed pace and urge authorities to ensure material supply and expedite completion.