Auditor General flags slow progress in transformational projects
Summary
The Office of the Auditor General has raised concerns over the slow progress of several key government transformational projects aimed at driving economic growth and development.
Key Points
- The Office of the Auditor General flagged slow progress in 17 priority transformational projects across economic, social, infrastructure, and governance sectors.
- The Galchhi–Trishuli–Mailung–Syafrubesi road project is only 64% complete due to local obstructions and land disputes, despite missing its deadline.
- Key transmission line projects like the Bheri Corridor and Tamor Corridor have low completion rates of 12.3% and 27.7%, respectively.
- The Auditor General urges government agencies to conduct mid-term reviews and calls for the National Planning Commission to more effectively monitor and resolve project bottlenecks.