BP Highway Reopens After Three-Day Closure Due to Flooding
Summary
The BP Highway, blocked for three days due to floods washing away diversions in the Roshi River area, has reopened after repairs. Traffic resumed from 3:30 PM on Monday with temporary diversions in place.
Key Points
- The BP Highway was obstructed for three days after floods in the Roshi River washed away diversions at multiple locations.
- The road division office announced that vehicular movement resumed from 3:30 PM on Monday.
- Affected areas included Chaukidanda, Ghumaine, Charasay Besi, Gimdi Besi, Narke, Chiuribas, Bokshikuna, Kaladhunga, Dalabeshi, Buldhunga, Mamti, Aaphghari, and Nepalthok.