Embankment work gathers pace to protect Susta from erosion

Summary

Construction of embankments is underway in Susta to protect the area from annual erosion caused by the Narayani river, with efforts focused on completing the project before the monsoon.

Key Points
  • Embankment construction started in Susta in March with a budget of Rs140 million to prevent erosion by the Narayani river.
  • The project aims to complete within 90 days before the monsoon to reduce the risk of land loss and flooding.
  • Around 175 labourers and 50 tractors are engaged daily for the construction along a one-kilometre stretch near the Susta suspension bridge.
  • Local government officials and the Ministry of Energy, Water Resources and Irrigation are closely monitoring the project progress and quality.