Fuel Shortage Stalls Kakarbhitta-Laukahi Road Construction
Summary
Construction of the Kakarbhitta-Laukahi road is stalled due to petroleum shortages caused by West Asian tensions, limiting bitumen and fuel availability.
Key Points
- Construction of Kakarbhitta-Laukahi road is delayed due to a shortage of bitumen and diesel fuel.
- Bitumen stock is sufficient for only 10-15 days amid peak paving season.
- Nepal Oil Corporation's diesel quota system restricts fuel supply to the project.
- If Middle East tensions persist, the project could halt completely within 7-10 days.