Tree marking has started for the transmission line construction under the Tanahun Hydropower Project, with significant progress in foundation and erection of towers along the Damauli-Bharatpur line. Various packages of the hydropower project are advancing steadily including dam and powerhouse construction.

Key Points
  • Tree marking has begun on trees in Chitwan district for the transmission line under the Tanahun Hydropower Project.
  • An agreement with the Department of Forest and Soil Conservation permits clearing land and removing trees in Chitwan and Tanahun.
  • KEC International Limited of India has completed foundation work for 78 out of 94 towers along the 33 km transmission line with 76% overall progress for this package.
  • Packages for dam construction and powerhouse are progressing, with Sonda Kalika JV and Sino Hydro Corporation handling different sections and significant milestones achieved.